On March 26, the Rabigh 4th Phase Seawater Desalination EPC Project in Saudi Arabia, undertaken by SEPCOIII, successfully completed 30 consecutive days of reliable operation, finishing ahead of the contractual schedule. This marks the full conclusion of the project’s installation, commissioning and trial operation, while also setting a record for the shortest construction period among similar units. The reliable operation officially commenced on February 23 and was carried out in an orderly manner across three phases, each lasting 10 days. During operation, the system maintained stable working conditions. Witnessed by the owner ACWA Power and the major owner SWCC, performance tests under various operating modes were successively completed at 60%, 80% and 100% load conditions. All water supply indicators met design and specification requirements, fully demonstrating the efficient and reliable operational performance of the entire plant, and earning high recognition and unanimous praise from the owner and all relevant parties.

|