The Saudi Qassim EPC Project the GT12 area achieved successful one-time backfeeding energization.

——

Date:2026-05-07     Source:SEPCOIII Author:SEPCOIII Fontsize:[ Big Middle Small ]

Following the successful one-time backfeeding energization of the GT11 area on May 6, the GT12 area of the Saudi Qassim EPC Project also achieved successful one-time backfeeding energization on May 7 local time.

Prior to energization, the project actively conducting detailed briefings on energization conditions, risk analysis, and safety measures to ensure all system equipment functioned properly and all parameters met required standards.During the energization process, operators worked closely with excellent coordination, while management personnel provided on-site supervision and support throughout the operation. The entire energization process was carried out accurately and smoothly, with all equipment systems operating steadily and reliably.