Saudi PP12 Combined Cycle Power Plant Expansion EPC project completes the concrete pouring of the raft foundation for the No. 12 waste heat boiler successfully

——

Date:2025-10-27     Source:山东电建三公司 Author:融媒体中心 Fontsize:[ Bing Middle Small ]

At 8:30 AM on October 26, the project successfully completed the concrete pouring of the raft foundation for the No. 12 waste heat boiler, with a single pour volume of 1,050 m³. This milestone follows the completion of the HRSG11 foundation pouring on October 16, marking the continued efficient and rapid progress of the combined cycle construction.

The pouring work commenced at 19:30 on October 25 and was successfully completed after 13 hours of continuous operation. To ensure construction quality and safety, the project team developed a detailed construction plan in advance, strictly implemented various control measures, and efficiently managed key processes such as concrete transportation, pumping, and vibration during the pouring process. This ensured that the entire operation remained safe, orderly, and under control.

The successful pouring of the No. 12 waste heat boiler raft foundation fully demonstrates the project team’s efficient coordination in process, resource allocation, and teamwork. It has created favorable conditions for the subsequent installation work of the combined cycle system. 