At
23:16 on April 28, the first grid connection of Unit 1 of Chuantou Luzhou
Project was successful, with all parameters running stably, laying a solid
foundation for the next 168 trial operation and commissioning
handover. In
order to ensure the smooth grid connection of Unit 1, the project made precise
deployment, clear organization and division of labor, communicated with the
owner, supervisor and commissioning personnel in advance for the program, the
project top management led the team to station in the centralized control room
to implement 24-hour shift duty, made it clear that the professional shift
leaders and duty inspectors, closely monitored the turbine, electrical and other
parameter changes, and carried out the whole tracking control; logistics
customized the “staggered meal schedule” and “staggered meal schedule” to make
sure that all parameters ran stable. The logistic department customized the
“staggered meal schedule” to send meals and warmth to the staff on duty in time,
which provided convenient support for the smooth grid connection of Unit 1.
Eventually, Unit 1 completed the generator short-circuit test, main transformer
impact test and other key tests with high quality and standard, realizing the
first successful grid connection, and the system is running smoothly at present,
and the parameters and indexes have fully met the standards. ![20250429174103950[1].jpg 20250429174103950[1].jpg](/cms_files/filemanager/1409533518/picture/20254/b11b3065269c43c896d2e20dc8c16b2a.jpg?t=0.7428126158494042)
|