At 7:36 AM on October 12, Unit 2 of the Chuantou Luzhou Project successfully connected to the grid on its first attempt. All parameters are operating stably, laying a solid foundation for the upcoming 168-hour trial operation and production handover. To ensure smooth grid connection, the project collaborated with the owner, supervisors, and commissioning personnel to execute meticulous planning. Detailed technical protocols and contingency plans were developed, ensuring every operator thoroughly understood the procedures. Technical briefing and safety mobilization meetings were convened to assign responsibilities to each position. Management teams conducted 24-hour patrols, closely monitoring parameter data and precisely adjusting equipment operation to guarantee all critical indicators met optimal standards. Ultimately, Unit 2 achieved its first grid connection attempt successfully. The system is currently operating stably, with all parameters meeting standards comprehensively. 
|